Sunday, October 05, 2008

Garage Progress

Work on the garage continues. Retaining walls are done and awaiting backfill. Garage and space above have been insulated and Chris, the builder, is now working on the flooring. He'll get cracking on the walls this week. Still waiting on gable windows. Entry door ordered and should be in Easley next Wednesday. Completed the framing for the deck this past week and looking forward to getting up there again this coming week to complete the decking.